EXTENSION OF REHAB SUBSTATION :
                 

1-

RURAL ELECTRIFICATION –WESTBANK(PALESTINE)
2 YEARS
COMPLETE INSTALLATION WORKS FOR 39 VILLAGES 33 & 11 KV & LV DISTRIBUTION NETWORK.
2-
JERUSALEMELECT. DIST. CO.
1 YEAR
TURNKEY 12 S/S 33/11 KV
3-
TABAQAT FAHEL PROJECT
EDCO
2000-2001
- COMPLETE ELECTRICAL WORKS FOR (4) OUTDOOR 33KV SWITCHGWEAR SUBSTATIONS. -COMPLETE TESTING AND COMMISSIONING FOR THE FOUR SUBSTATIONS.
4-
MUTAH UNIVERSITY 33/11 KV. SUBSTATION
MUTAH UNIVERSITY
1998-1999

SUPPLY, INSTALLATION, AND TESTING AND COMMISSIONING FOR AMODIFICATION OF 33/11 KV SUBSTATION. THE WORKS INCLUDE:-

SUPPLY AND INSTALLATION BATTERY CHARGER 48VDC.

- SUPPLY AND INSTALLATION BATTERY CHARGER 24 VDC.

- SUPPLY AND INSTALLATION OF INDOOR AND OUTDOOR C.T’s.

- SUPPLY AND INSTALLATION OF METERING AND PROTECTION RELAYS(SEPAM SERIES).

- REMOVE ALL THE CONTROL CONNECTIONS AND REINSTALL NEW CONNECTIONS IN NEW CONFIGURATION.

- RECONNECT CONTROL CONNECTIONS BETWEEN SWITCHGEAR AND GENERATOR SETS.

- PROVIDE AS BUILT DRAWING FOR ALL ELECTRICAL WORKS.

5-
PLG – UPGRADING TENDER 34/97
CEMENT FACTORY
1997-1998

INSTALLATION TESTING AND COMMISSIONING OF THE FOLLOWING:· -PLC SYSTEM – 4000 POINT·

-MCC’S AND MV SWITCHGEAR·

-POWER TRANSFORMER·

-FREQUENCY DRIVE·

-LOCAL PANELS, CABLE TRAYS, CONDUITS·

-MV AND LV CABLES·

-CONTROL SYSTEM COMPONENTS ( LCB’S, CDB’S , LS, …Etc) ·

-INSTALLATION OF CONTROL SYSTEM I/O PC 65 AND REMONTE I/O’S PC 62,PC 63·

-INSTALLATION OF INSTRUMENT DEVICES

(IDB’S,SS,TS,PS,PO2.S,VIB,..ETC). ASSOCIATED WITH CABLE TERMINATION , TESTING AND COMMISSIONING

6-
ARAB POTACH COMPANY CONTRACT 71/94 “NEW BRINE INTAKE PUMPING STATION
ARAB POTASH CO.
JUNE 1997

SUBCONTRACTOR TO CEGELEC (EQUIPMENT SUPPLIER) FOR THE INSTALLATION OF ELECTRICAL WORKS. THE PROJECT CONSISTS MAINLY OF 4PUMPS, OF 2900 kW INSTALLED CAPACITY, COMPLETE WITH ALL ASSOCIATED ELECTRICAL & INSTRUMENTS EQUIPMENT.EMC SCOPE OF WORK INCLUDED BUT NOT LIMITED TO THE INSTALLATION, TESTING & COMMISSION OF THE FOLLOWIN:·

-15 MVA, 33 kV/6.0 kV POWER TRANSFORMERS.·

-1 NO, INDOOR 33 kV SWITCHBOARD·

-5 CUBICLES OF 6.6 kV METAL CLAD SWITCHGEAR·

-ALL CABLE LADDERS/TRAYS WORK·

-5000M OF MV CABLES.·

-LV & CONTROL DESKS ·

-ALL ASSOCIATED CONTROL & INSTRUMENTATION EQUIPMENT.·

-LV MCC’S & CONTROL DESKS·

-LV DISTRIBUTION SYSTEM, LIGHTING AND SMALL POWER DEVICES.

7-
ARAB POTASH EXPANSION PROJECT
ARAB POTASH
1993-1994

SUBCONTRACTOR TO MERLIN GERIN ( EQUIPMENT SUPPLIER) TO WIMPEY & AIRMECH FOR INSTALLATION TESTING AND COMMISSIONING THE FOLLOWINGS:-

-29 CELLS OF 11 kV METAL CLAD INDOOR SF6 SWITCHGEAR ( TESTING , TERMINATION & COMMISSIONING)-

-6 CUBICLE OF 33 kV SWITCHBOARD ( EXTENSION TO THE EXISTING

- 3.3 kV MOTOR CONTROL CENTERS (ABOUT 13 CUBICLES). (TESTING, TERMINATION & COMMISSIONING).

- 33 kV , 11 kV & LV CABLES ( IN ASSOCIATION WITH WIMPEY)

- 15 kV CABLE JOINTS & TERMINATION OF HARVESTERS CABLES, ON SEA WATER FLOATING LINE.

- CABLE TRAYS AND LADDERS

.- 15 KM of 33 kV OVER HEAD LINE.

8-
MV DISTRIBUTION PROJECT
JORDAN ELECTRIC POWER CO.
4 MONTHS1992

ERECTION, TESTING COMMISSIONING AND MAINTENANCE OF ALL ASSOCIATED ELECTRICALWORK.THE WORK INCLUDED THE FOLLOWING:

-20 NO’S 1000 KVA PAD MOUNTED PACKAGED SUBSTATIONS.

-10 NO’S 1500 KVA PAD MOUNTED PACKAGED SUBSTATIONS.

9-
REHABILITATION OF MV DISTRIBUTION NETWORK AT Q.A.I AIR PORT
CIVIL AVIATION AUTHORITY
6 MONTHS 1989
SUPPLY, INSTALLATION TESTING & COMMISSIONING OF 21 KM MV UNDER GROUND CABLES AT QUEEN ALIA INTERNATIONAL AIR-PORT FOR REHABILITATION OF THE DISTRIBUTION NETWORK.SUPPLY INSTALL TEST & COMMISSIONEING OF 4 PACKAGE SUBSTATIONS.
10-
ARAB DRIP CO.
ARAB DRIP CO.
8Weeks 1986

DESIGN SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF ALL ELECTRICAL WORKS COMPRISING ·

*NEW MAIN DISTRIBUTION BOARDS.·

*MANUAL CHANGE OVER SWITCHES.·

*CABLE TRAYS, LADDERS AND CABLES TO PRODUCTION LINE EQUIPMENT AND TO THREE ELECTRICAL EQUIPMENT.·

*INSTALLATION OF PRODUCTION EQUIPMENT AS

- MOULDING MACHINES

- EXTRUDERS

- AIR COMPRESSORS… ETC.·

*EARTHING SYSTEM.·

*TESTING & COMMISSIONING.

11-
QUEEN ALIA INTERNATIONAL AIR PORT
CIVIL AVIATION AUTHORITY
1980-1982

INSTALLATION TESTING & COMMISSIONING OF:

· MV SWITCH BOARDS (33 KV & 11 KV).

-RING MAIN UNITS (11 KV) ·

-300 KM OF AIRFIELD CABLES (POWER & COMMUNICATIONS).·

-DIESEL ENGINES GENERATING SETS.·

-TRANSMISSION LINES.·

-AIR FIELD LIGHTING TOWERS AND STREET LIGHTING.·

-ALL NECESSARY AUXILIARY CONTROL EQUIPMENT

- NAVIGATION SYSTEM·

-CABLES TERMINATION AND INTERCONNECTION ·

-UPS & BATTERY CHARGERS.·

-EARTHING SYSTEM.

12-
WADI AL– YUTUM PUMPING STATION
WATER SUPPLY CORPORATION
6 Month 1979

SUPPLY, INSTALL TEST & COMMISSION OF COMPLETE ELECTRICAL WORKS FOR 7 PUMPING STATIONS INCLUDING DIESEL- GENERATOR SETSTHE WORK INCLUDED BUT NOT LIMITED TO THE FOLLOWING:·

MAIN 33/0.4 kV SUBSTATION WITH ALL POWER & CONTROL EQUIPMENT.·

7 PUMPING STATION, 100 KVA EACH WITH MOTOR CONTROL CENTERS AND CONTROL EQUIPMENT.·

ALL PUMPS AND PIPE WORKS ·

MV & LV DISTRIBUTION CABLES·

MV O.H.L WETWORKS·

ALL INSTRUMENTS AND INSSTRUMENTATION WORKS.

13-
IRBID MAIN SUBSTATION (230/122/33 kV)
JORDAN ELECTRICITY AUTHORITY
1977-1979

INSTALLATION OF THE FOLLOWING:·

-BUS WORKS·

-132/230 kV OIL CIRCUIT BREAKER ( OUTDOOR)·

-STEEL STRUCTURES·

-ALL MV & LV CABLES, TRENCHES, TRAY AND LADDER SYSTEMS.·

-ALL INDOOR RELAY & CONTROL PANELS.·

-PROTECTION & CONTROL EQUIPMENT ·

-INDOOR METAL CLAD SWITCHGEARS ·

-EARTHING SYSTEM.

THIS PROJECT IS REGISTERED AS ONE OF THE LARGEST SIMILAR ELECTRICAL PROJECT CONDUCTED BY LOCAL SUBCONTRACTOR SINCE 1979.

 

 

 


 
<<Back     Next>>